50 Barry Street

  • Address
    50 Barry Street, Carlton
    VIC 3053
    Type

    Residential

    Year

    2024

  • Team

    Project Manager
    Kevin Maher

    Cost

    $450,000

Project Information

The Barry’s Street project was an extensive recladding effort, undertaken as part of the Victorian Government’s Cladding Rectification Program and overseen by St Ferrer in collaboration with Cladding Safety Victoria. Over the course of 16 weeks, our team worked meticulously to remove and replace over  450m² of high-risk cladding on this residential building. The non-compliant materials were replaced with compliant HVG Facades 3mm Mondoclad panels in bronze metallic and champagne colors, significantly enhancing both the building’s safety and its aesthetic appeal.

Removed over 450m² of non compliant cladding

  • Non compliant cladding was disposed responsibly into waste bins

Installed over 450m² of HVG Mondoclad installed

  • Installed in bronze metallic and champagne colours

Installed of colorbond flashings

  • Installed new Colorbond flashings to balconies and overflows
Back to all Projects