WHL Vermount

  • Address
    408-410 Burwood Highway,
    Vermont South, VIC
    Type

    Library

    Year

    2023

  • Team

    Project Manager,
    Kevin Maher

    Size

    2,675m2

    Cost

    $950,000

Project Information

The development, led by Women’s Housing Limited and designed by Architects Clarke Hopkins Clarke, entrusted Arc3 Construction with the project. Castle was tasked with overseeing the cladding and metal works for the multi-story housing project. These residences provide safe housing solutions for families and young children seeking refuge from domestic violence. The cladding installation totaled 1188m², including Colorbond, MondoClad, Knotwood Vertical Shadowline, Versilux, and Equitone. The balustrades and screens covered a total of 500m², with a balustrade system of 250m² and screens totaling 250m². Additionally, the project included the installation of Ronstan Cable Trellis, Colorbond Capping, Pergola Battens, and Axiom Metropolis Glass Balustrades.

1188m² of Cladding

– 675m² of Colorbond
– 220m² of 3mm Mondoclad
– 196m² of Knotwood Vertical Shadowline
– 72m² of 6mm Versilux
– 25m² of Equitone

 

250m² of Balustrades

– 250m² of Balustrade System and support systems

250m² of Screens

– 100m²perforated aluminium screens with a matt black powder-coat finish
– 150m² aluminium Screens

220lm of Pergola Battens

– 220lm of battens powder-coated in Dulux charcoal finish

Cable Trellis Installation

– Castle team provided installation of Cable Trellis

Axiom Metropolis Glass Balustrades

– Castle installed a 650mm High heat-soaked glass balustrade system

235lm of Colorbond capping

– 235lm of Colorbond capping’s installed with Colorbond monument finish

On this project, we engaged with a diverse range of materials from solid aluminium to Colorbond and fibre cement cladding, alongside balustrades and intricate metal works. This project illustrates our diverse range of capabilities.